Grantham station development works are part of the Carillion Inter-City Express Platforms (IEP) Programme which includes Stevenage, Newark Northgate, Northallerton, Durham and Darlington.
The works require a 14m extension at one end (3m wide) and, due to the location of a signal gantry, a 2m extension to and island platform at the other platform end.
The actual working hours on both platforms were 14 hours.
Installation is now complete.